We Budgeted 25,000 for Our Kitchen Extension and Ended Up Spending 41,000

, by Meabh Boyle, 4 min read, Costs and Budgeting

kitchen extension build

We got three quotes. We hired someone we liked. We had a budget with a contingency built in. We did, more or less, everything you're supposed to do. And we still ended up sixteen thousand euro over what we planned to spend.

I'm not writing this to complain. The kitchen extension we built onto the back of our house in County Kildare is, genuinely, the best thing we've done to the property. But the gap between what we expected to pay and what we actually paid was big enough that I think it's worth being honest about, because I don't see that honesty very often.

Here is where the money actually went.

The original quote left a lot out

Our builder quoted 24,500 for the extension itself. Groundworks, block walls, a flat roof with a rooflight, underfloor heating, plastering, windows and a set of sliding doors. We added five hundred to round up to a tidy number and called it our budget.

What the quote did not include, and what we did not think to ask about, was the connection between the new extension floor and the existing kitchen floor. They were at different levels. Levelling that out, doing the screed, and sorting the transition cost just under two thousand euro on its own. Not a huge number, but it wasn't in anyone's head when we signed off.

The quote also didn't cover the electrical work as a separate line. Our electrician, who came in after the builder, charged 2,800 for the extension alone, new consumer unit upgrade included. That was a separate invoice we hadn't provisioned for separately.

The kitchen itself was its own project

This is where I think we were most naive. We had budgeted roughly 8,000 for a new kitchen, which felt reasonable. What we hadn't fully worked out was that pulling out the old kitchen, moving the sink, relocating a radiator, tiling the floor, and fitting the new units and appliances were four or five separate jobs involving four or five separate trades, and they don't always line up neatly.

There was a week where the kitchen fitter couldn't come back until the plumber finished, and the plumber couldn't quote properly until the kitchen layout was confirmed. We lost time, and time with trades costs money even when nobody is technically doing anything wrong.

The kitchen itself came to closer to 11,500 once everything was done. If you're planning something similar, what I wish I'd known before gutting our 1970s semi-D kitchen covers a lot of this coordination problem better than I can in a paragraph.

We made three decisions mid-build that added real money

First, we upgraded the rooflight. The one in the original spec was fine. We saw a bigger one on a site visit to another job and changed our order. That cost an extra 900 and pushed out the timeline by nearly two weeks while we waited for the new unit.

Second, we decided to move a stud wall that had always annoyed us, since we were already in the middle of a building project and it felt like a now-or-never moment. The builder was happy to do it. It cost 1,400.

Third, and this was the one that genuinely stung, we decided late in the project to upgrade the external wall insulation and do a proper job of the airtightness. We'd been reading about retrofits and energy ratings and decided we didn't want to do half a job. That decision was probably the right one long-term, but it added roughly 2,200 to the build cost with very little warning.

Mid-build changes are expensive almost every time. I knew that in theory. I did it anyway, three times.

The contingency was too small and we spent it too early

We had set aside 2,500 as a contingency, which felt generous at the time. It was gone by week four, mostly on the floor level issue and a drainage problem that nobody had flagged during the initial survey. After that, every unexpected cost came straight out of whatever was left in our current account.

A proper contingency for a project like ours, based on what I now know, should have been closer to 15 percent of the total build cost. On a 25,000 project that would have been 3,750. It still wouldn't have covered everything, but it would have taken more of the sting out of the first few surprises.

If you want to understand how costs are broken down before you commit to anything, getting a quantity surveyor to look over your quote is genuinely useful. Understanding a quantity surveyor's report before you sign anything is something we wish we'd done before we started.

What I'd price differently next time

I'd cost the kitchen and the extension as two fully separate projects with two separate budgets, and I'd make sure every trade had a written scope before they started. I'd also resist any decision made on site that wasn't in the original plan, at least until I'd slept on it for a night.

The extension is brilliant. The food is better, the mornings are better, the whole ground floor feels different. I'd do it again tomorrow. I'd just go in expecting to spend closer to 40,000 than 25,000.